Zip Code:266200
Website:www.jhconcretepump.com
E-mail:Sales@jiuhezg.com
Tel:+86-13553011266
Fax:+86-532-88562569
Add:No.9 Wanglan Road, Longquan Street, Jimo, Qingdao.
In order to guaranteeing maintenance man safety,it is necessary to build up a platform for checking and maintaining the concrete placing boom on the floor.
1. periodic inspection
1.1 Daily inspection
● Inspect if the electrical control system works normally or not before operating.
● Inspect whether the hydraulic oil level which is 1ower than the half of the oil tank or not,and the hydraulic oi1 is emulsified or not.
● Check if the hydraulic system lines leak。
● Check the direction of rotation of the pump.
● Check if the balance valve which work reliably or not.
1.2 Weekly inspection
● Check whether the connecting bolts,the end clamping plates,pins and 1ock nuts 1ooseness or not.
● Check the delivery pipes and change the pipes immediately when the thickness of the pipes is less than 2 millimeters.
Act as the following to prolong the service life after approximately 6000m3pumped volume:
Rotate the bends through180°of the delivery line.
Rotate the all delivery pipes through 120°of the delivery line
● Check whether the cotter pins of the railing drop off or not.
1.3 Monthly inspection
● Check whether the slewing limit switch work normally or not.
● Check if the slewing reducer works abnormally.
● Tighten the connecting bolts of the tower section.
● Check the shaft coupling of the motor.
● Check the motor,the insulation resistance of the circuit,the metal shell of the electrical equipment,and the earthed resistance of the metal structure.
● Visual inspection of electrical cable,repair and change it after burn in or breakage.
● Fully check and maintain a11 the parts of the equipment including hydraulic and electrical components.
2. Lubricate
Pour grease to the mobile pins periodically.